An update from site: Central Parade (May 2022)
This update from site comes from Central Parade, our site in Perivale, London Borough of Ealing.
We are building 57 units for shared ownership and affordable rent for our client, A2 Dominion.
Andrew Ziadi is our Project Manager on site, and brings us the latest news.
“Scaffold striking is nearing completion across the site, with both the South and East elevations completely struck. Also, the Tower Crane strike will be completed before the end of May too.
External groundworks are busy, with slabbing and curbs starting in the courtyard area.
Inside, the show flats have now been de-snagged, ready for our client A2Dominion to begin the dressing process.
Elsewhere, 2nd Fix within the units are nearing completion and kitchens are being installed. The feature stonework is also almost complete.”
For more information, view the Central Parade project page here.